Penentuan Jalur Kritis Dalam Manajemen Proyek Pada Pembangunan Gedung Convention Hall And Exhibition Center UPI
Abstract
Project management is the planning, organizing, directing, and controlling of a company's resources to achieve predetermined short-term goals that have been set by top-level management. This definition emphasizes that project management includes a variety of processes that integrate a company's resources to achieve specific project goals. In a project, there are various options that can be used to do scheduling. One form of scheduling is by using the CPM method. The purpose of this study is to find out the critical path in the UPI Convention Hall and Exhibition Center Building Construction project. The critical path method, or CPM, is a method that can be used in project planning and supervision. In this study, the author is interested in discussing the analysis of the critical path in the construction of the UPI Convention Hall and Exhibition Center Building using the CPM method. This study uses a quantitative descriptive approach with secondary data in the form of an S-curve. Therefore, the creation of CPM network diagrams must have the longest duration according to the plan. Based on the results of the research, it was obtained that the critical path in the construction of the UPI Convention Hall and Exhibition Center Building occurred in two paths or in two work activities, namely in CA – B.II.2 activities where these activities were in standard architecture activities and in roof cover structure activities with a duration of 147 days and 63 days respectively, therefore the total duration acquisition was in accordance with the project plan, which was 210 days.
Keywords:
Construction Management; CPM; Critical Path; Project
Abstrak
Manajemen proyek adalah perencanaan, pengorganisasian, pengarahan, dan pengendalian sumber daya perusahaan untuk mencapai tujuan jangka pendek yang telah ditentukan yang telah ditetapkan oleh manajemen tingkat atas. Definisi ini menekankan bahwa manajemen proyek mencakup berbagai proses yang mengintegrasikan sumber daya perusahaan untuk mencapai tujuan proyek tertentu. Pada sebuah proyek terdapat beragam pilihan yang dapat digunakan untuk melakukan penjadwalan. Salah satu bentuk penjadwalan adalah dengan menggunakan metode CPM. Tujuan dari penelitian ini adalah untuk mengetahui jalur kritis pada proyek Pembangunan Gedung Convention Hall and Exhibition Center UPI. Metode jalur kritis atau CPM, merupakan metode yang dapat digunakan dalam perencanaan serta pengawasan proyek. Pada penelitian kali ini penulis tertarik untuk membahas mengenai analisa terhadap jalur kritis pada Pembangunan Gedung Convention Hall and Exhibition Center UPI dengan menggunakan metode CPM. Penelitian ini menggunakan pendekatan deskriptif kuantitatif dengan data sekunder berupa kurva S. Pada Pembangunan Gedung Convention Hall and Exhibition Center UPI ini direncanakan akan selesai dalam kurun waktu 210 hari. Maka dari itu pembuatan diagram jaringan CPM harus memiliki durasi paling lama sesuai dengan perencanaan. Berdasarkan hasil penelitian diperoleh jalur kritis pada Pembangunan Gedung Convention Hall and Exhibition Center UPI ini terjadi pada dua jalur atau pada dua aktivitas pekerjaan, yaitu pada kegiatan CA – B.II.2 dimana kegiatan tersebut adalah pada kegiatan arsitektur standar dan kegiatan struktur penutup atap dengan masing masing durasi 147 hari dan 63 hari. Maka dari itu total perolehan durasi sudah sesuai dengan perencanaan proyek yaitu 210 hari.
Kata Kunci:
CPM; Jalur Kritis; Manajemen Konstruksi; Proyek
Keywords
Full Text:
PDFReferences
Alamsyah, A., Ismail, R. S., & Hidayat, T. (2020). Analisa perhitungan pekerjaan reparasi kapal dengan metode critical path method (CPM). SPECTA Journal of Technology, 4(1), 84–91.
Ervianto, W. I. (2023). Manajemen Proyek Konstruksi. CV. Andi Offset.
Fatimah, A., Akmal, A., Agusmaniza, R., & Rahmah, C. Y. (2023). Analisis faktor yang mempengaruhi tenaga kerja bersertifikasi terhadap kesuksesan proyek konstruksi di Kota Banda Aceh. VOCATECH: Vocational Education and Technology Journal, 5(1), 70–81.
Hasibuan, E. S., Siregar, E. B., Batubara, F. H., Rambe, M. V. R., & Lubis, R. S. (2022). Time management analysis of administrative implementation in the North Sumatra Provincial Forestry Service using the CPM method. Jurnal IPTEK Bagi Masyarakat, 2(2), 60–68.
Jawat, I. W., Gita, P. P. T., & Dharmayoga, I. M. S. (2020). Kajian metoda pelaksanaan pekerjaan pondasi bored pile pada tahap perencanaan pelaksanaan. PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa, 9(2), 126–142.
Kartini, I., Abdullah, A., Riauwati, J., Yoeliastuti, Y., Tannady, H., Khasanah, K., Batubara, H. C., Kamisi, H. La, & Liana, W. (2022). Manajemen proyek. Cendikia Mulia Mandiri.
Mar’aini, M., & Akbar, Y. R. (2022). Penentuan jalur kritis untuk manajemen proyek (studi kasus pembangunan Jalan Selensen-Kota Baru-Bagan Jaya). Jurnal Pustaka Manajemen (Pusat Akses Kajian Manajemen), 2(1), 6–13. https://doi.org/10.55382/jurnalpustakamanajemen.v2i1.184
Marbun, V. V., Gawei, A. B. P., & Puspasari, V. H. (2023). Penjadwalan proyek pada pembangunan Puskesmas Kota Besi. Jurnal Teknika: Jurnal Teoritis Dan Terapan Bidang Keteknikan, 6(2), 65–74.
Nono, Y., Pratasis, P. A. K., & Malingkas, G. Y. (2019). Analisis metode nilai hasil terhadap waktu dan biaya pada proyek Office and Distribution Center, Airmadidi, Minahasa Utara-Manado. Jurnal Sipil Statik, 7(11), 1465–1477.
Nugraha, A. D., & Waskito, J. P. H. (2023). Evaluasi pelaksanaan proyek dengan metode CPM dan PERT (studi kasus proyek pekerjaan finishing lanjutan pembangunan Gedung Program Studi Desain Interior Tahun 2019 Kampus ITS). Axial: Jurnal Rekayasa Dan Manajemen Konstruksi, 11(2), 79–90.
Perdana, A. (2021). Analisa manajemen waktu pada proyek konstruksi dengan menggunakan metode jalur kritis/CPM (critical path method) (studi kasus pembangunan perumahan tipe 36 di Pekanbaru). Universitas Islam Riau.
Puspitasari, D. P., Purwono, N. A. S., & Poerwodihardjo, F. E. (2022). Analisis perbandingan penjadwalan proyek dengan metode CPM, PERT, Kurva-S (studi kasus peningkatan Jalan Menganti Kesugihan). Teodolita: Media Komunkasi Ilmiah Di Bidang Teknik, 23(1), 77–89.
Putri, Y. E., Yuli, E., & Siska, A. (2023). Analisa penerapan manajemen waktu pada pembangunan rumah type 36 di Jalan Lintas Sumatera Desa Suko Mulyo Kecamatan Martapura Kabupaten Ogan OGAN Komering Ulu Timur. Concrete Design Journal, 1(2), 10–18.
Siahay, M. C., Ahmad, S. N., Gusty, S., Supacua, H. A. I., Ampangallo, B. A., Rachman, R. M., Latupeirissa, J. E., & Maitimu, A. (2023). Pembangunan infrastruktur di Indonesia. TOHAR MEDIA.
Silmi, N., Kurniawan, B., & Subhan, M. (2024). Perencanaan dalam ilmu pengantar manajemen. Journal of Student Research, 2(1), 106–120.
Siswanto, A. B., & Salim, M. A. (2019). Manajemen proyek. CV. Pilar Nusantara.
Sugiyanto, S., & Insan, K. (2022). Penerepan optimalisasi metode critical chain project management pada pelaksanaan proyek konstruksi. Rang Teknik Journal, 5(2), 352–363.
Sugiyarto, S., Qomariyah, S., & Hamzah, F. (2013). Analisis network planning dengan CPM (critical path method) dalam rangka efisiensi waktu dan biaya proyek. Matriks Teknik Sipil, 1(4), 408–416.
Sulistia, D., & Agustina, I. D. (2023). Penjadwalan proyek dengan kurva-S pada pembangunan perumahan di Kota Bekasi. Jurnal Al Ulum LPPM Universitas Al Washliyah Medan, 11(2), 100–106.
Tamzidhillah, M. F., & Waskito, J. P. H. (2022). Percepatan pelaksanaan proyek menggunakan metode CPM dan PERT (studi kasus proyek pekerjaan konstruksi lanjutan F-MIPA Tower Menara Sains tahun 2020 Kampus ITS). Axial: Jurnal Rekayasa Dan Manajemen Konstruksi, 10(2), 87–95.
Wicaksono, R. A., & Safirin, M. T. (2025). Evaluasi dan optimalisasi durasi pelaksanaan system test menggunakan metode critical path method dengan software POM-QM di PT. XYZ. Jurnal Serambi Engineering, 10(1), 12062–12069.
Zid, C., Kasim, N., & Soomro, A. R. (2020). Effective project management approach to attain project success, based on cost-time-quality. International Journal of Project Organisation and Management, 12(2), 149–163.
DOI: https://doi.org/10.38038/vocatech.v6i2.200
Refbacks
- There are currently no refbacks.
VOCATECH : Vocational and Technology Journal
Unit Penelitian dan Pengabdian Masyarakat & Penjaminan Mutu
Akademi Komunitas Negeri Aceh Barat
Komplek STTU Alue Peunyareng, Ujong Tanoh Darat, Meureubo, Kabupaten Aceh Barat, Aceh 23615
Telp. (0655) 7110271
Email: vocatech@aknacehbarat.ac.id
VOCATECH: Vocational Education and Technology Journal Published by:
Unit Penelitian dan Pengabdian Masyarakat & Penjaminan Mutu
Akademi Komunitas Negeri Aceh Barat
Indexed by:

VOCATECH: Vocational Education and Technology Journal Creative Commons Attribution-ShareAlike 4.0 International License.